===2017 HLF bid===
{{As of|2017|04}} the Trust has another bid under consideration seeking approximately £1 million funding from the HLF for a large part of the £1.26 million cost. It has plans to raise additional funds from other sources. The HLF will decide in the summer of 2017 whether the second bid has made it through to the next stage of the process, and would make a final decision in September 2018. If successful in securing HLF support, the SVR would intend to complete this urgent project in two stages by 2020.<ref>[http://svrtrust.org.uk/our-projects/falling-sands-viaduct.html 'Falling Sands Viaduct', Severn Valley Railway Charitable Trust website] (Retrieved 27 April 2017)</ref>