Changes

Jump to: navigation, search

Falling Sands Viaduct

177 bytes added, 23:51, 9 December 2021
highly commended at the National Railway Heritage Awards
Repair work began at the very end of December 2019 with the lifting of the track by a team of volunteers and paid staff. External contractors then removed the ballast and fill from the viaduct. After the infill was removed, the contractors improved the drainage channels and added a waterproof membrane, before putting everything back together. These works were essentially complete when interrupted in March by [[2020 coronavirus disease (COVID-19) pandemic|coronavirus disease (COVID-19)]], although track was not joined and signalling not yet in place.
While the railway remained closed, the contractors began work on stage 2. Easing of lockdown restrictions allowed work on stage 1 to restart in the week of 19 June, with laying of rail completed on 25 June. The following day [[BR Class 50 50035 Ark Royal]] became the first train to cross the viaduct since December while delivering S&T equipment for the new [[Ground Frames at Foley Park|Foley Park ground frame]].<ref name="bljul20">[https://www.svrlive.com/bljul20 Branch Lines, July 2020]</ref> Discovery of roosting bats held up repairs while a licence was obtained from Natural England to allow work to be carried out.<ref name="bljul20"/> Work recommenced in August,<ref>[https://www.svrlive.com/blsep20 Branch Lines newsletter, September 2020] (Retrieved 29 August 2020)</ref> and the civil engineering work was completed in mid-December with the final piece of corbelling being slotted into place. The contractors then left the site.<ref name=bljan21>[https://www.svrlive.com/bljan21 Branch Lines, January 2021]</ref>  On 1 December 2021 the project was highly commended at the [[Awards|National Railway Heritage Awards]]<ref>[https://www.svrlive.com/bldec21 Branch Lines, December 2021]</ref>.
<gallery>
Trustworthy, administrator
6,649
edits

Navigation menu