Changes

Jump to: navigation, search

Falling Sands Viaduct

336 bytes added, 21:51, 17 July 2020
Exhibition and roosting bats!
In June 2017 the Trust secured £71,800 of HLF financial backing to develop a bid seeking £927,000 from the HLF for a large part of the quoted £1.324 million total project cost. The SVR met the challenge of raising matched funding of £397,000 (originally £275,000) for which the Trust co-ordinated efforts through a campaign entitled "'''Helping hands for Falling Sands'''". Preliminary structural investigations in Summer 2018 had revealed two gas mains, one live, which increased the cost and SVR's contribution.
The Trust submitted its bid on 26 October 2018 and on 25 March 2019 announced the award of a further £853,800 grant from The [[:Category:Lottery funding#National_Lottery_Heritage_Fund|National Lottery Heritage Fund]] which together with the earlier grant took the total amount of its funding to £925,600. The grant, along with other funds raised, will be was used to restore Falling Sands the Viaduct and to launch an exciting a programme of community engagement and exhibitions that will explore the Railway’s early history. In August 2019 the Trust unveiled a large donation wall at [[The Engine House]] acknowledging the individuals, organisations and businesses who had donated to the "Helping Hands for Falling Sands" appeal, and in 2020 an exhibition was held there. [[LMS 2886 Six-wheel Passenger Brake (later 32919)|LMS six-wheel Passenger Brake 2886]] was adapted to host a mobile exhibition.
===2019-20 repair work===
Repair work began at the very end of December 2019 with the lifting of the track by a team of volunteers and paid staff. External contractors then removed the ballast and fill from the viaduct. After the infill was removed, the contractors improved the drainage channels and added a waterproof membrane, before putting everything back together. These works were essentially complete when interrupted in March by [[2020 coronavirus disease (COVID-19) pandemic|coronavirus disease (COVID-19)]], although track was not joined and signalling not yet in place.
While the railway remained closed, the contractors began work on stage 2. Easing of lockdown restrictions allowed work on stage 1 to restart in the week of 19 June, with laying of rail completed on 25 June. The following day [[BR Class 50 50035 Ark Royal]] became the first train to cross the viaduct since December while delivering S&T equipment for the new [[Ground Frames at Foley Park|Foley Park ground frame]].<ref>[https://www.svrlive.com/bljul20 Branch Lines, July 2020]</ref>Discovery of roosting bats held up repairs while a licence was obtained from Natural England to allow work to be carried out<ref>[https://www.svrlive.com/bljul20 Branch Lines July 2020]</ref>.
<gallery>
Trustworthy, administrator
6,650
edits

Navigation menu