2022 upgrade project: on time and on budget
*Environmental measures including water harvesting and LED lighting to give full illumination throughout the building.
*Installing an 8-tonne overhead travelling crane, allowing heavy items to be moved safely and with ease.
 
In September 2021 the Charitable Trust announced the project was to be phased, with the main phase concentrating on the roof and all associated works necessary, including the foundations for the crane and electrical works.
In early 2021 the Charitable Trust launched its "Home and Dry appeal". The project was the subject of the spring 2021 [[:Category:SVR fundraising lotteries|"Home and Dry" raffle]].<ref>SVR News 212, 213</ref><ref>[https://www.svrlive.com/blmar21 Branch Lines, March 2021]</ref>
The quoted cost of the project escalated. SVR News Winter 2020 quoted a figure of £80,000. The Charitable Trust's planned 2020 appeal had aimed to raise £250,000. The Home and Dry appeal was for a revised project cost of £425,000, later increased to £475,000 because of the 'spiralling cost of steel and additional improvements that are needed inside the works'.<ref>[https://www.svrlive.com/blaug21 Branch Lines August 2021]</ref> When the project was phased, the first phase costs amounted to £380,000. By November 2021 phases 1 and 2 of the project were funded and in project delivery, consisting of the roof, electricals, cladding, ground works and civils works. On 25 January 2022 the Charitable Trust announced that the whole £475,000 has had been raised.<ref>[https://www.svr.co.uk/2022/01/25/the-severn-valley-railway-is-home-dry/ SVR Website] (retrieved 18 February 2022</ref>. Although it was intended the crane would be installed laterA small further appeal of £15, secured funding allowed the Railway to order a second-hand 6.3 ton capacity crane and supporting steel structure to be installed as part of the works000 covered improved epoxy resin flooring.<refname=blaug22>[https://www.svrlive.com/blnov21 bldec21 Branch Lines November 2021, August 2022]</ref>
Contractors arrived on site in April 2022, with areas out of bounds including the main locomotive shed and paint shop. Work was expected to take until AugustA second-hand 6.3 ton capacity crane and supporting steel structure were installed as part of the works.<ref>[https://www.svrlive.com/blnov21 Branch Lines November 2021]</ref> The works were completed on time and on budget.<ref name=blaug22/>
==Machine Shop ==