| style="vertical-align:top;" | 24. To perform night work if required || The Contractor shall carry on by night work any of the work which the Engineer may call upon him so to do without his being entitled to any additional payment for such night work.
|-
| style="vertical-align:top;" | 25. Workmen to be paid once a fortnight<br>Office for Resident Engineer || The workmen employed by the Contractor shall be paid in cash at least every fortnight in an Office or Offices to be erected for the purpose and the Contractor shall also provide a convenient office for the Resident Engineer on the works.  
|-
| style="vertical-align:top;" | 26. Acceptance of work || No work shall be considered as completed unless accepted in writing by the Engineer. 
|-
| style="vertical-align:top;" | 27. Contractor to keep open Railways, etc. || The Contractor, at his own cost, shall keep open, where required, all existing Railways, roads, footpaths, sewers, canals, rivers, etc, free from obstruction at all times during the term of the Contract.  
|-
| style="vertical-align:top;" | 28. And to make good damage to railways, etc. || The Contractor shall also be liable for, and shall make good any damage or injury to Railways, Canals and Roads whether public or private, and to contiguous or adjoining lands, buildings or property and to watercourses, sewers, drains, culverts, pipes, telegraphs etc, occasioned by the acts or defaults of himself his agent, servants or workmen of from any cause whatever contingent upon the execution of the works done or omitted by himself for his own purposes as Contractor; and shall take upon himself any liability of the Company to compensate owners and occupiers of buildings and land for temporary damage, and shall pay the costs of all suits and trials which may arise from these causes but this shall not include any compensation which in the ordinary course would be payable by the Company for the injurious affecting of lands, buildings or other property such as the interference with light access, water, etc not occasioned by the acts or defaults of the Contractor or his Agents or Servants.  
|-
| style="vertical-align:top;" | 29. Contractor not to sell sand, etc, excavated || The Contractor shall not sell or otherwise dispose of, or remove except for the purpose of the Contract, or as herein mentioned and sand, stone, clay soil or other materials of any kind or description whatsoever, which may be obtained from the excavations, cuttings or embankments from any lands in the possession of the Company. 
|-
| style="vertical-align:top;" | 30. The Company to pay as follows. || The Company shall, and in manner hereinafter mentioned, pay to the Contractor for the work done under this Contract, such prices and sums of money as are hereinafter provided. 
|-
| |
|}
 
25 Workmen to be paid once a fortnight
Office for Resident Engineer
The workmen employed by the Contractor shall be paid in cash at least every fortnight in an Office or Offices to be erected for the purpose and the Contractor shall also provide a convenient office for the Resident Engineer on the works.
 
26 Acceptance of work
No work shall be considered as completed unless accepted in writing by the Engineer.
 
27 Contractor to keep open Railways, etc.
The Contractor, at his own cost, shall keep open, where required, all existing Railways, roads, footpaths, sewers, canals, rivers, etc, free from obstruction at all times during the term of the Contract.
 
28 And to make good damage to railways, etc.
The Contractor shall also be liable for, and shall make good any damage or injury to Railways, Canals and Roads whether public or private, and to contiguous or adjoining lands, buildings or property and to watercourses, sewers, drains, culverts, pipes, telegraphs etc, occasioned by the acts or defaults of himself his agent, servants or workmen of from any cause whatever contingent upon the execution of the works done or omitted by himself for his own purposes as Contractor; and shall take upon himself any liability of the Company to compensate owners and occupiers of buildings and land for temporary damage, and shall pay the costs of all suits and trials which may arise from these causes but this shall not include any compensation which in the ordinary course would be payable by the Company for the injurious affecting of lands, buildings or other property such as the interference with light access, water, etc not occasioned by the acts or defaults of the Contractor or his Agents or Servants.
 
29 Contractor not to sell sand, etc, excavated
The Contractor shall not sell or otherwise dispose of, or remove except for the purpose of the Contract, or as herein mentioned and sand, stone, clay soil or other materials of any kind or description whatsoever, which may be obtained from the excavations, cuttings or embankments from any lands in the possession of the Company.
 
30. The Company to pay as follows.
The Company shall, and in manner hereinafter mentioned, pay to the Contractor for the work done under this Contract, such prices and sums of money as are hereinafter provided.
31. Monthly Certificates of the work done.