| style="vertical-align:top;" | 21 Contractor to copy Drawings and be responsible for setting out || The Contractor shall provide at his own cost copies of all the drawings required in carrying out his contract and shall be responsible for the correct setting out of the Works and for the completion there of in conformity with the Specification and with the Drawings. |-| | |style="text-align:center;" |'''List of Drawings'''
|-
| style="vertical-align:top;" | 22. | | No. 1 General Plan of Railway<br>&nbsp;“ &nbsp; &nbsp; 2 Longitudinal Section of Railway<br>&nbsp;“ &nbsp; &nbsp; 3 Cross Sections (Sheet 1)<br>&nbsp;“ &nbsp; &nbsp; 3a Cross Sections (Sheet 2)<br>&nbsp;“ &nbsp; &nbsp; 4 Cross Sections of Railway Cuttings + Embankments and Road approaches<br>&nbsp;“ &nbsp; &nbsp; 5 Gates and Fencing<br>&nbsp;“ &nbsp; &nbsp; 6 Bridge at 0m 46.88 <br>&nbsp;“ &nbsp; &nbsp; 7 Tunnel from 1m 4 Ch<span style="vertical-align:super;font-size:small">s</span> to 1m 26 <br>&nbsp;“ &nbsp; &nbsp; 8 Bridge at 1m 61.15 <br>&nbsp;“ &nbsp; &nbsp; 9 Bridge at 1m 7 Ch<span style="vertical-align:super;font-size:small">s</span> and Culverts<br>&nbsp;“ &nbsp; &nbsp; 10 Viaduct from 2m 11.63 Ch<span style="vertical-align:super;font-size:small">s</span> to 2m 17.72 <br>&nbsp;“ &nbsp; &nbsp; 11 Bridge at 2m 26.72 <br>&nbsp;“ &nbsp; &nbsp; 12 Bridge at 2m 46.30 <br>&nbsp;“ &nbsp; &nbsp; 13 Division at River Stour and Canal  
|-
| style="vertical-align:top;" | 23. Contractor not to absent himself and to assist in measuring || The Contractor shall not absent himself from the Works without having a fully authorised and competent Agent to act in his stead and shall give the Engineer or his assistants all personal assistance by himself and his Agents and workmen and all labor and materials required in setting out (or in checking his setting out) the work from time to time during the progress of the works. 
|-
| style="vertical-align:top;" | 24. To perform night work if required || The Contractor shall carry on by night work any of the work which the Engineer may call upon him so to do without his being entitled to any additional payment for such night work.  
|-
| |
|}
 
21 Contractor to copy Drawings and be responsible for setting out
The Contractor shall provide at his own cost copies of all the drawings required in carrying out his contract and shall be responsible for the correct setting out of the Works and for the completion there of in conformity with the Specification and with the Drawings.
 
List of Drawings
22
No. 1 General Plan of Railway
“ 2 Longitudinal Section of Railway
“ 3 Cross Sections (Sheet 1)
“ 3a Cross Sections (Sheet 2)
“ 4 Cross Sections of Railway Cuttings + Embankments and Road approaches
“ 5 Gates and Fencing
“ 6 Bridge at 0m 46.88 Chs
“ 7 Tunnel from 1m 4 Chs to 1m 26 Chs
“ 8 Bridge at 1m 61.15 Chs
“ 9 Bridge at 1m 7 Chs and Culverts
“ 10 Viaduct from 2m 11.63 Chs to 2m 17.72 Chs
“ 11 Bridge at 2m 26.72 Chs
“ 12 Bridge at 2m 46.30 Chs
“ 13 Division at River Stour and Canal
 
23 Contractor not to absent himself and to assist in measuring
The Contractor shall not absent himself from the Works without having a fully authorised and competent Agent to act in his stead and shall give the Engineer or his assistants all personal assistance by himself and his Agents and workmen and all labor and materials required in setting out (or in checking his setting out) the work from time to time during the progress of the works.
 
24 To perform night work if required
The Contractor shall carry on by night work any of the work which the Engineer may call upon him so to do without his being entitled to any additional payment for such night work.
25 Workmen to be paid once a fortnight